Rome wasn’t built in a day, and neither will all the upgrades and new construction that Mesa voters approved when they passed the $196-million city bond issue. In fact, all the projects won’t be completed until mid-2024. Here is the schedule laid out by Mesa for implementing the projects under the bond issue approved by voters in November. 

The city’s list goes by fiscal years, which begin July 1 and end the following June 30. In addition to these projects, the city Fire and Medical Department will be spending $24.7 million over the next five years to buy new equipment, mainly pumpers and ladder trucks.

FY 2018-19

Total spending: 14.9 million

Land acquisition for: the Eastmark fire station, Monterey Park, North Center Street ballfields, Northeast public safety facility.

Design for: communication fiber, City Center Plaza, Dobson Library improvements, Federal Building renovation, Harris Basin playground, i.d.e.a Museum phase 1, Lehi Crossing shared use path, Main Library improvements.

FY 2019-20

Total spending: $27.8 million

Design for: Eastern Canal shared use path, Federal Building renovation, i.d.e.a. Museum phase 1, Lehi Crossing shared use path, Monterey Park, Northeast public safety facility, Red Mountain Park community soccer and youth baseball/softball fields.

Construction starts for: City Center Plaza, communication fiber, Dobson Library improvements, Eastmark fire station, Harris Basin playground, Main Library upgrades.

FY 2020-21

Total spending: $30 million

Design for: Eastern canal path, Northeast public safety facility, Red Mountain fields, Signal Butte Park second stage, Southeast Mesa Library.

Construction: City Center Plaza, Lehi Crossing path, communication fiber, Federal Building rehab, Eastmark fire station, Monterey Park, North Center Street ballfields.

FY 2021-22

Total spending: $49.6 million

Design for: Crismon and Elliot basin, dog park at Countryside Park, i.d.ea. Museum Phase 1, Marlborough Mesa Park, Pao Verde park, police evidence facility, Southeast Mesa library.

Construction: communication fiber, Eastern Canal and Lehi Crossing paths, Monterey Park, North Center Street ballfields, Northeast public safety facility, Red Mountain fields, Signal Butte Park second phase.

FY 2022-23

Total spending: $57.4 million

Construction: Crismon and Elliot basin, Countryside Park dog park, i.d.e.a. Museum, Marlborough Mesa Park, North Center Street ballfields, Northeast public safety building, Palo Verde Park, police evidence facility, Signal Butte Park phase 2, Southeast Mesa Library.

FY 2023-24

Total spending: $16.3 million

Construction: Crismon and Elliot basin, Countryside dog park, i.d.e.a. Museum phase 1, police evidence facility and Southeast Mesa Library.

(0) comments

Welcome to the discussion.

Keep it Clean. Please avoid obscene, vulgar, lewd, racist or sexually-oriented language.
PLEASE TURN OFF YOUR CAPS LOCK.
Don't Threaten. Threats of harming another person will not be tolerated.
Be Truthful. Don't knowingly lie about anyone or anything.
Be Nice. No racism, sexism or any sort of -ism that is degrading to another person.
Be Proactive. Use the 'Report' link on each comment to let us know of abusive posts.
Share with Us. We'd love to hear eyewitness accounts, the history behind an article.